Construction Updates & Projects

Updated 11/26/2018

1. 212th Street & Interurban Trail Improvements

Crews plan to work on any remaining punchlist items, new mailbox installation at a revised location and install the Pedestrian Crosswalk Barriers (upon completion and WSDOT inspection/approval at the galvanizers), then finish with the remaining signage that is attached to the pedestrian crosswalk barriers, including revisions. Note, there may be some intermittent traffic impacts during the work operation along 212th St SW from 61st PL W through 63rd Ave W.

2. 2018 City -Wide Restriping



Restriping will continue intermittently during the week.  Expect occasional traffic impacts on all city streets where striping currently exists.  Drive carefully throughout the City as you encounter the striping trucks and follow their traffic control directions as they place temporary traffic cones in the areas they will be working.

3. Terrace Station - South Side of 236th St. SW east of I-5 NB Off-Ramps



Utility work will be conducted this week on Gateway Blvd. Expect trucks and trailers entering and exiting the site on 236th St. SW and exiting on 244th S. SW.

4. 55th Ave. W south of 234th St SW



Grading and early utility work will begin this weekend on a townhome project. Expect shoulder encroachment and lane closures on 55th Ave. W during daytime hours.

5. 216th St. SW between 66th Ave. W and 61st Pl. W

Utility conduit is being installed on the north side of 216th St. SW. Expect shoulder encroachment and lane shifts on 216th St. SW during daytime hours.